The school faced a tight deadline with their athletics schedule: the first soccer game of the season,which would also serve as the debut of their new state-of-the-art LED board and audio system. While most projects of this size and scale take 14-18 weeks from point of signing until completion,the school needed the system ready to go in 8 weeks.
To do this, we had to expedite:
Securing approvals and permits and consolidating a standard construction schedule into half the usual time.
Rearranging the schedule and booking external operational partners to meet the timeline while pre-building all needed hardware and equipment to keep the project on schedule
28’-3”W x 15’-9”T full-matrix 10.00mm LED display with 140 degree viewing angle on new monopole structure
Fully integrated single point MTS speaker system for full stadium coverage
Decorative Steel Truss with backlit signage package, branded audio scrim and uplighting